Projected RFP, Vendor Selection and Project Timeline
We anticipate a 9-15 month project timeframe with site launch occurring during a semester break, either over the summer (May-early August or during January winter break).
Please Note: This is an anticipated project timeline that is subject to change.
RFP distributed | Feb. 6 |
Deadline for submitting questions | Feb. 18 |
Responses to questions provided | Feb. 25 |
Proposals due | March 6 |
Notification of interview All firms will be notified of their status, whether they have been invited for an interview. | March 13 |
Video conference interviews with finalists | March 23-27 |
Onsite presentation by finalists | April 22-24 |
Firm selected The project will begin as soon as possible after selection, pending contract and statement of work completion. | April 30 |
Possible site visit to firm’s office by AVP for Digital Strategy | May 4-7 |
Onsite discovery Two days of onsite discovery meetings or workshops with campus stakeholder groups. | June 1-5 |
Discovery phase complete | July 17 |
Anticipated website launch The website would be launched at the end of the academic year and following campus commencements ceremonies. | Summer 2021 |